UGMK to invest 5 bln roubles into development of Gaysky GOK in 2013
Edited by Rhod Mackenzie / 2013-03-20 07:14:22
The investment into the capital construction of the Gaysky GOK (enterprise of the raw materials complex of UGMK) in 2013 will make up 5 bln roubles. The priority direction is the construction of pits of the underground mine which is a part of the project of stripping and development of deep horizons of the underground mine of the Gaysky GOK at 830-1,100 m. Its realization will allow to increase the productivity of the mine from 5.6 to 7 mln tons of ore a year.