Metinvest continues to invest in Yenakiyevo metallurgical plant
Edited by Rhod Mackenzie / 2014-12-03 02:06:08
After the forced interruption because of military operations, workers carry out blowing of the third blast furnace at EMZ - DP-3 with useful volume of 1719 cubic meters. The complex of commissioning works originally should be performed by foreign experts, but the fighting forced them to leave the industrial site. Therefore, the plant created a working group of workers, which accompanied the process of the commissioning. The launch of the new unit was preceded by mandatory "hot" tests.