Electrozinc to invest 224 mln roubles into capital repair
Edited by Rhod Mackenzie / 2016-02-03 06:23:37
There has been confirmed capital construction plan for 2016 with the financing volume of 224 million roubles at the plant Electrozinc (part of UGMK). Completion of construction of three new facilities of sulfuric production has been designed into the investment programme. They are 2 washing towers, a drying tower and sanitary pipe. According to the schedule, connection of the new equipment to the production chain will take place in autumn during annual shutdown maintenance of zinc production.