Construction of Power of Siberia to cost 170-180 bln roubles to Gazprom in 2016
Edited by Rhod Mackenzie / 2016-06-29 01:32:08
Gazprom plans to spend 170-180 bln roubles on the construction of Power of Siberia in 2016, the deputy chairman, A. Kruglov, said.
In 2016 it will be by 10% less than we planned – 170-180 bln roubles, he said.
Previously the deputy chairman of Gazprom, V. Markelov, said that in 2016 it is planned to construct 400 km of pipelines. The plan for 2017 is at least the same. In 2017 the financing will make up 250 bln roubles, Kruglov said.