Gas via the "Power of Siberia" pipeline to start in 2018.

The delivery of pipes for the "Power of Siberia" gas pipeline and mastering the Chayandinsk field are on schedule. On the eve one of the last batches for this year was delivered into the port of Lena. The correspondent of STRC "Amur" learned what kind of work is possible in the harsh winter of Yakutia, and when the natural gas comes in Blagoveshchensk.

The most important cargo is well casing for the appraisal wells. The mastering of Chayandinsk oil and gas field has not yet begun in full scale. However, "Gazprom" delivers the basic materials now - until the summer navigation ends. The deliveries via the river are the most economically advantageous. In addition to the pipes the road plates go into the port of Lena. The site of the deposit is in fact the taiga now. And in order to get started, you should first build the infrastructure in the area.

Full text available to premium subscribers only.

Buy full access for 24 hours now

or

Request a quote to subscribe for a longer period

Oil and Gas, Metals and Mining, News from Russia and neighbouring countries
12 Northfields Prospect; London, - SW18 1PE; United Kingdom
E 51° 27.454518" S 0° 14.101236"

Theme by Danetsoft and Danang Probo Sayekti inspired by Maksimer