Production drilling at the Uvat group of fields increases by 24.3%
~~On the preliminary results of the first nine months of 2013, RN-Uvatneftegaz increased its production drilling at the Uvat group of fields by 24.3% as compared with the same period of the last year. Besides, the next headway record was set at the Ust-Tegusskoye field – 1321 meters per day. The previous achievement – 1118 meters – was registered in 2012.
On the whole, the enterprise plans to construct 136 production wells before the end of the year and 17 of them will be horizontal. The average start yield of horizontal wells, constructed this year, makes up 162 tons of oil per day. This exceeds the average production rates at traditional wells almost two times.