Throughput capacity expansion of South-Caucasus pipeline to be over in 2018
Edited by Rhod Mackenzie / 2013-03-12 05:56:03
The project of the expansion of the South-Caucasus pipeline (SCP) will be completed in 2018.
The land purchase for the project will start in 2013 and will be over in 2014.
The initial works on the project will start in 2014 and the main works on the pipeline’s construction – in early-mid 2015 and will be over in 2017.