Penzaenergo continues the reconstruction of 110 kV Sursk Substation.
Edited by Rhod Mackenzie / 2014-09-10 08:44:28
The Branch of JSC "MRSC of Volga" (included in the "Rossetti" group of companies) - "Penzaenergo" started the reconstruction of the 110/35/10 kV "Sursk" substation provided by the investment program of the company.
The 110/35/10 kV "Sursk" Substation was commissioned in 1965. It is equipped with a transformer type TDTNG15000/110 and TDTNG16000/110 with already obsolete MCP-110 oil circuit breakers. The ORU-110 kV equipment also requires replacement.