STEP has gained permission to start fit out Lukoil’s head-office in Saint-Petersburg
Edited by Rhod Mackenzie / 2014-06-03 10:49:14
The construction company STEP has completed the construction works at the office of Lukoil in the Petrograd district of Saint-Petersburg. Now the general contractor is installing the general utilities, develops the closely located area and holds interior decoration works which are ready by 60%.
Moreover, the façade works are almost over: they are ready by 80%. The works at the project are completed y 75% in general. The State Construction Supervision and Inspection Service has issued permission for putting into operation of Lukoil’s head-office