Sibnefteprovod has completed welding of the second stage of Zapolyarye-Purpe oil pipeline
Edited by Rhod Mackenzie / 2014-07-02 12:55:51
Sibnefteprovod has completed the welding of the second stage of Zapolyarye-Purpe oil pipeline within the planned dates, despite hard climatic and natural conditions. Now the company prepares for hydraulic testing for the durability and vacuum rating of the linear part that will last until the end of July. The welding and assembling of the second stage was started at the beginning of 2013.